Location: La Selva del Camp
Developer: Progrés Selvatà, SLM
Project Manager: Mr. Josep Martí
Start date: July 2006
End date: June 2007


This project included the construction of a new indoor pool in the sports area in La Selva del Camp, attached to the sports centre, built a few years before. The facilities consist of different swimming pools (1 competition pool and the rest, recreational)and the work was conducting wall foundations, pillars, the glasses, the pavement of the basement, walls, pillars and floor structure; the floors are supported by a concrete structure of pillars and beams of reinforced concrete; the floor surrounding of the pools is made of perforated brick pillars