With the beginning of this month of August, the project of “Tomb de Muralles” from the Town Hall of La Selva del Camp took a step further. After the opening of the various proposals, has been awarded to Constècnia 3, SL the execution of the works included in this project.

The work to be carried out consists of the demolition of existing non-adequate elements, the explanation and paving and the realization of service networks of the “Raval Sant Pere”, the “Raval Sant Rafael” and “Passeig Josep Cristià”. To carry out this work different interventions will be carried out in each and every one of the “Tomb de Muralles” points, thus improving the current state and the general aspect of the area.

The works will be carried out for 8 months and to try to minimize the impact on the population will be carried out with 4 different phases:

  • PHASE 01: Work will begin on the stretch between “Els Ponts” and “Plaça de la Palma”.
  • PHASE 02: You will continue along the stretch between “Plaça la Palma” and “Sant Agustí”.
  • PHASE 03: Next there will be the section between “Els Ponts” and the “Portal de Mates”.
  • PHASE 04: And finally, the works with the section between the “Portal de Mates”, the “Cantó del Vaqué” and the “Passeig Josep Cristià”.

Next September the works of the first phase of the work will begin, marking a priority to minimize the possible inconvenience to the neighbours in the area.